23.02.038 Changes to approved project.
An approved land use shall be developed or established only as shown on
the project plans approved as part of the permit application, except where
otherwise provided by this section. Deviation of project design or construction
from the approved plans, and changes to the project after completion of
construction may occur only as follows:
(1) Except as provided by subsection
(2) of this section, a feature of the use or project subject to the standards of
Chapters 23.04, 23.05, 23.07 or 23.08, may be modified provided that the change
requested is in conformity with the standards of this title. Such change is to
be requested in writing with appropriate supporting materials and explanation of
the reasons for the request. The planning director may approve a requested
change upon verification of its conformity with this title; provided that, such
approval shall not modify the effective date of the land use
permit.
(2) Where the environment coordinator determines that the change
results in an increased impact to an aspect of the project that was specifically
addressed in a negative declaration or environmental impact report of the
project, or the change relates to a project feature that was specifically
addressed in conditions of approval of a minor use permit or development plan,
or that was a specific consideration by the review authority in the approval of
a minor use permit or development plan, a new minor use permit or development
plan approval shall be obtained. (Ord. 2715 § 24, 1995; Ord. 2649 § 4,
1993; Ord. 2344 § 1 (Exh. A) (part), 1988)