Title 23 COASTAL ZONE LAND USE
Chapter 23.08 SPECIAL (S) USES
23.08.182 Permit requirements for surface mining.
(a) New Surface Mining Operations. Development plan approval shall be
obtained before starting any surface mining operations as defined in this
chapter, except as provided in subsection (b) of this section. New mines shall
be limited to a maximum of one operator per site, and such operator shall take
full responsibility for reclamation per Section 23.08.184.
(b) Existing
Surface Mining Operations. A person who has obtained a vested right to conduct a
surface mining operation before January 1, 1976, need not secure a permit as
required by subsection (a), as long as the vested right continues and there are
no substantial changes. All operations are required to have an approved
reclamation plan and financial assurances per Sections 23.08.183 and 23.08.184.
Provided, however, that development plan approval is also required if an
existing mine is changed by increasing the on-site processing capabilities of
the operation or by changing the method of mining (i.e. from mechanical to
hydraulic technology), or the mine is expanded beyond the external boundaries of
the original surface mining site.
(c) New Operations on a Reclaimed Site.
The resumption of surface mining operations on a site where reclamation was
previously completed shall only occur pursuant to the approval of a new
development plan and reclamation plan.
(d) Vested Right Defined. For the
purposes of surface mining operations only, a person is deemed to have a vested
right if, prior to January 1, 1976, he has in good faith and in reliance upon a
permit or other authorization, if a permit or other authorization was required,
diligently commenced surface mining operations and incurred substantial costs
for work and materials necessary therefor. Expenses incurred in obtaining an
amendment to the land use element, or the issuance of a permit to establish or
expand a mine, are not deemed costs for work or materials.
(e) Surface
Mining Permit Review Procedure. The department of planning and building will
review the permit application and the reclamation plan for accuracy and
completeness, and coordinate review of the application and plan with the State
Department of Conservation and other agencies. A public hearing will be
scheduled after the filing of both the permit application and the reclamation
plan. The public hearing will be held pursuant to Section 23.01.060. The purpose
of the hearing will be to consider the applicant’s request and to approve,
conditionally approve or disapprove the issuance of a permit and reclamation
plan for the proposed surface mining operation. Approval or conditional approval
may be granted only upon making the findings that the application and
reclamation plan or amendments to reclamation plan and reports
submitted:
(1) Adequately describe the proposed operation in sufficient
detail and comply with applicable state mandated requirements of
SMARA;
(2) Incorporate adequate measures to mitigate the probable
significant adverse environmental effects and operational visual effects of the
proposed operation;
(3) Incorporate adequate measures to restore the site to
a natural appearing or otherwise usable condition compatible with adjacent
areas;
(4) Show proposed uses which are consistent with the county general
plan; and
(5) Demonstrate that the uses proposed are not likely to cause
public health or safety problems.
In addition, when any significant
environmental impact has been identified, the findings mandated by the Public
Resources Code shall be made. (Ord. 2715 § 141 (part), 1995: Ord. 2592
§ 9 (part), 1992)
<< previous | next >>